I-70 Improvements from TR Hughes Blvd. to Hwy. K

I-70 Improvements from TR Hughes Blvd. to Hwy. K
Owner: City of O'Fallon
Scope: Utility Coordination subconsultant to EFK Moen. Responsible for locating all utilities within the project limits. Performed records research to assemble facility maps for utilities within the project limits. Oversight of topographical survey, related to utilities, to ensure that they are captured accurately and completely. Single point of contact between project and utility owners. Coordinating closely with utility representatives to make them aware of project related details and identify/address issues as early as possible. Reviewing design plans for potential utility conflicts. Coordinating with utility companies to gather information related to cost and schedule for potential relocations associated with design build project.
Projected Construction Cost: $16 Million
Completion: TBD

Replacement of Schoettler Rd. Bridge over Creve Coeur Creek

Schoettler Rd. Bridge
Owner: City of Chesterfield
Scope: Utility Coordination subconsultant to Burns & McDonnell. Responsible for locating all utilities within the project limits. Performed records research to assemble facility maps for utilities within the project limits. Oversight of topographical survey, related to utilities, to ensure that they are captured accurately and completely. Single point of contact between project and utility owners. Coordinating closely with utility representatives to make them aware of project related details and identify/address issues as early as possible. Reviewing design plans for potential utility conflicts. Coordinating with utility companies to gather information related to cost and schedule for potential relocations associated with design build project.
Projected Construction Cost: $1.7 Million
Completion: TBD

I-44 Design Build Support Services

Interstate 44
Owner: MoDOT
Scope: Utility Coordination subconsultant to HR Green. Responsible for locating all utilities within the project limits. Performed records research to assemble facility maps for utilities within the project limits. Oversight of topographical survey, related to utilities, to ensure that they are captured accurately and completely. Single point of contact between project and utility owners. Coordinating closely with utility representatives to make them aware of project related details and identify/address issues as early as possible. Reviewing design plans for potential utility conflicts. Coordinating with utility companies to gather information related to cost and schedule for potential relocations associated with design build project. Creation of comprehensive utility tracking report and writing of utility related sections of the ITP, RFQ, and RFP project documents.
Projected Construction Cost: $21.7 Million
Completion: May 2015

I-44 Improvements from Mraz to Geyer

Interstate 44 and Meramec River
Owner: MoDOT
Scope: Engineering services for the replacement of the I-44 bridges over the Meramec River in Fenton, MO and associated interchange modifications from west of the Mraz Road to east of Geyer Road.
Size: 3.25 Miles
Construction Cost: Approximately $75 Million
Designer: TBD
Builder: TBD
Design Completion: TBD
Goal: Project will replace deficient bridge structures on I-44 crossing the Meramec River and modify interchanges to provide additional capacity.

Poplar Street Bridge Complex

Poplar Street Bridge Complex
Owner: MoDOT
Scope: Rebuild the ramp connections between I-64 and I-55/I-70 at the Poplar Street Bridge and widen the Poplar Street Bridge over I-55/I-70.
Size: Approximately .25 miles
Construction Cost: $46.2 Million
Designer: HNTB
Builder: TBD
Design Completion: October 2013
Goal: Project will allow for increased traffic capacity at this interchange, by widening the bridge and increasing ramps from one lane to two.

I-64 Daniel Boone Bridge Design-Build

I-64 Daniel Boone Bridge Design-Build
Owner: MoDOT
Scope: This project will replace the existing 80-year-old westbound I-64 bridge. Construction will include replacement of the bridge deck on eastbound I-64, and new approach pavement on the north and south ends of the structure.
Size: 3.75 miles
Construction Cost: $125 Million
Designer: Burns & McDonnell
Builder: Walsh/Alberici Joint Venture
Construction Completion: December 2015
Goal: The Boone Bridge project will replace an obsolete bridge over the Missouri River, to enable better traffic flow and access between St. Louis and St. Charles.

I-70/Washington Ave./3rd St. Punch-Through

I-70/Washington Ave./3rd St. Punch-Through
Owner: MoDOT
Scope: This punch-through will provide new ramp access from westbound I-70 to Washington Ave. and Washington Ave. to eastbound I-70. Construction will include new access from northbound 3rd St to westbound I-70.
Size: 0.5 miles
Construction Cost: $15.6 million
Designer: EFK Moen
Builder: TBD
Design Completion: March 2013
Goal: Improved accessibility and traffic maintenance as part of the MoDOT “Park Over the Highway” Project, more broadly incorporated into the St. Louis Gateway Arch Grounds CityArchRiver 2015 initiative to “create an experience under the arch as memorable as the arch itself.”